Current Construction Updates

School

Start

Open

Percent Complete

Maps, Pictures, and more

Rebuild Spanish Fork High School

Spring 2022

Fall 2024

100%

SFHS details

Rebuild Payson High School

Spring 2023

Fall 2025

70%

PHS details

Rebuild Springville High School

Spring 2024

Fall 2026

40%

SHS details

Addition Landmark High School

Spring 2024

Fall 2025

21%

LHS details

2018 Bond Updates

Project

Status

Actual or Estimated Start Date

Actual or Estimated End Date

Construction Bid and Actual or 
Estimated Other Costs

Final Cost

Valley View Middle School

Completed

February 2019

August 2020

 $ 37,972,701 

 $ 37,972,701 

Spring Canyon Middle School

Completed

February 2020

August 2021

 $ 39,085,861 

 $ 39,085,861 

Maple Grove Middle School

Completed

February 2020

August 2021

 $ 39,188,946 

 $ 39,188,946 

Spanish Fork High School

In Progress

June 2020

August 2024

 $ 127,431,753 

TBD

Payson High School

In Progress

June 2022

August 2025

 $ 143,024,495 

TBD

Springville High School

In Progress

December 2022

August 2026

 $ 177,683,183 

TBD